The construction of the H2 vertical plant ends

Infrastructures Division

At the Bournezeau site (85), the H2 vertical plant of Hoffmann Green Cement Technologies completes its elevation to a final height of 70 metres. In total, our Eiffage GĂ©nie Civil teams poured 2,200 m3 of low-carbon concrete per day into an impressive 1. 80 m sliding formwork.

Last July, our teams laid 24 petals of 15 tons each, prefabricated on site with concrete from H-UKR 0% clinker cement, to form the inverted cone of the plant.

Made entirely of Hoffmann Green Technologies concrete, the new unit will be commissioned by the end of 2022, with a production capacity of 250,000 t of zero-carbon cement or clinker. Ultimately, it will enable the production of all current and future Hoffmann Green Cement Technologies technologies.

Congratulations to our 56 companions mobilized 7/7-24/24h on this exceptional construction site.