Two-thirds of the planned 3 million m³ have now been excavated, permanently transforming the landscape to prepare the ground for the future nuclear programme.
Commitment and technical precision remain at the heart of daily operations:
- The ongoing installation of 15,000 m² of soil nailing, essential for ensuring the long-term stability and durability of the slope.
- Continuous shift work operations, driven by one absolute priority: the safety of everyone on site.
Congratulations to all the Fougerolle Ballot, Roland, Tinel, Forézienne and Charier teams on the ground for their dedication to meeting this engineering challenge.