In the South: a new operational quay, 154 m long, offering a depth of 15 m.
In the North: 300 m of quays, with a depth of 16 m, have also been handed over. This achievement comes in addition to the 400 m of quays delivered in early 2026.
These new quays are now in operation by the Autonomous Port of Cotonou (PAC).
To date, the cumulative project figures are:
- 700 m of quays built with a depth of -16 m
- 154 m of quays built with a depth of -15 m
- Over 1.5 million m³ dredged
- 61,000 m³ of concrete poured
- 24,000 m² of paving stones laid
- 3,250 tonnes of reinforcement steel used
Teams are continuing operations for the next expansion phases of the North quay, in collaboration with port representatives and the project engineer, TME (Tanger Med Engineering).
Congratulations to our dedicated teams as well as those of our partners, Spie batignolles Fondations and ADEOTI SA, on reaching this new project milestone!
Credit: Eiffage