CDG Express: Eiffage Rail completes 7 weeks of intense work

In zones D (Porte de la Chapelle), E (Gare du Bourget) and F (Mitry-Mory), Eiffage Rail has built 2,400 m of RVB, laid 5 switches, excavated 15,000 m3 of material, built 60 piles (retention basin) and 600 m of hydraulic structures.

This work, carried out under temporary interruption of rail traffic, was the subject of considerable preparation and mobilized 150 people, taking turns day and night, from June 26 to August 15.

Congratulations to all those involved in the success of this operation!