The service order will be delivered in April by the Siaap (Paris region public sanitation service). The project deadline is 66 months, including a 19-month design period (until 2018) and a 35-month works phase to be launched in early 2019.
Eiffage Genie Civil has already completed several structures linked to the plant's modernization programme launched in the early 2000s. The most recent to date, known as Biosav, was commissioned on 21 February 2017.