Working in a constrained environment with challenging access, our experts rose to the challenge in just 5 weeks, repairing a major cavity of nearly 50 m³ as well as various areas of scouring at the toe of the dam.
A highly technical operation in a few key figures:
- 60 m² of inverted formwork installed
- 65 m³ of colloidal concrete poured using a downstream filter curtain
- 10 hours of helicopter lifting required to supply the site
Congratulations and a huge thank you to all the teams involved, who successfully combined technical expertise and agility on this unique project!