This is a source of immense pride for all our teams who, over the last 4 years, have brought this 4-km series of structures to life, crossing through the towns of Saint-Jean-de-Maurienne and Villargondran.
An exceptional project in numbers:
- 5 km of retaining walls, reaching up to 16 m in height
- 1.3 million m³ of embankments
- 1 viaduct over the Arvan river and 1 rail bridge to reinstate the RD906 road
- 3 hydraulic culverts and 3 technical galleries for track access under the embankments
- 1 structure for the tracks to pass through the future passenger building
- 6 km of 4-meter-high acoustic barriers
- 800 m of new platforms in the Saint-Jean-de-Maurienne station
To finalize this phase, an exceptional 4-week, high-intensity operation mobilized our teams day and night to connect the new infrastructure to the existing rail network.
A huge congratulations to all the teams for their work on this major project!
We thank SNCF Réseau for their continued trust and remain mobilized for the start of phase 3 in the coming weeks.