The ceremony was held on January 30th, attended by Benin's Minister of Living Environment and Transport, in charge of Sustainable Development; representatives from the Port of Cotonou and Benin Terminal; as well as the project owner, Tanger Med Engineering.
During the event, several of our team members were formally recognized for their outstanding commitment to safety and prevention on-site.
Just a few days after the handover, this new section of the port welcomed its first vessel, marking an immediate start to its operational life.
The Project in Numbers:
- 400 meters of new quays constructed to a depth of 16 meters.
- 4,200 tons of steel utilized.
- 400,000 paving stones laid.
-
21,000 m³ of concrete poured.
Congratulations to our dedicated teams, as well as to our partners Spie Batignolles Fondations and ADEOTI SA, on the successful completion of this major project phase!