Eiffage Civil Engineering connected the two banks of the Singrobo-Ahouaty dam in Ivory Coast

Ramo de Infraestruturas

At the Singrobo-Ahouaty hydroelectric dam, the two banks are now connected, the earthworks phase is completed, and the hydraulic equipment is in place!

  • Installation of a rock fill embankment over 1,400 meters, involving the excavation of 800,000 cubic meters of materials directly from the site.
  • Commencement of the commissioning of hydraulic gates assembled by STPH - HWP Group.
  • Assembly of the 2 horizontal axis Kaplan turbines by GE Renewable Energy: in progress.

​It's worth noting that this dam is intended to deliver a power of 44 megawatts (MW) to the Ivorian interconnected grid. It will also supply power to the surrounding villages: Singrobo, Ahouaty, Ahénémou 2, Pacobo, and N’Dènou.

A design-build project with RMT from Eiffage Energy Systems, on behalf of Ivoire Hydro Energy, the project's concessionaire.